
|
Before In the Beginning ... Deconstruction Teardown Construction Week 6 - The Footings Week 7 - The Foundation Week 8 - Plumbing Week 9 - Backfill Week 10 - Framing 1 Week 11 - Framing 2 Week 12 - Electrical Week 13 - Siding 1 & Insulation Week 14 - Siding 2 Week 15 - Drywall My Vacation Week 16 - Floors Week 17 - Concrete & Electrical Week 18 - Plumbing Week 19 - Trim Week 20 - Porch Rail Week 21 - Concrete Finish Week 22 - Punch List Week 23 - Casings Week 24 - Miscellaneous Week 25 - Priming Week 26 - Painting Week 27 - Outside Week 28 - Move In Week 29 - Finishes Week 30 - Garden Week 31 - Permits Week 32 - Flashing & Doors Week 33 - Yard Work Week 34 - Doors Week 35 - Basement Week 36 - Final Payment On My Own The List Odd Bits Unusual Aspects HOME |
Week 27 - Outside
This week started out with rain, but was supposed to clear later, so I decided to hold off painting for a while. Instead I worked on a variety of little jobs: finishing the floor in the office; getting stuff into the dumpster, since I'm having it picked up next week; retrofitting my garage sale find into another rain barrel - and modifying my existing rain barrel so they could be ganged together. I also picked up and dropped off a variety of materials, including a couple of mirrors from the The Rebuilding Center. One will go in the hall and the other is for the bathroom. Later in the week I moved back outside. ![]()
The biggest task was the cement/vinyl siding transition, which I couldn't do until I got the necessary j-channel, but I had saved a lot of the old vinyl siding and I wanted to get everything I didn't need into the dumpster. For better access, the first thing was to drain and remove the existing rain barrel. ![]()
As it turned out, the siding itself was relatively easy to replace, except where I had to work it under an already installed piece, but even that wasn't too difficult. I also wanted to remove the second unused ground drain and re-capping it because it obstructed the rain barrel. In the end I decided to pull up the pavers and cap it low enough that I could replace the pavers right over the top of it, which I did. ![]()
I put the first rain barrel back all the way into the corner, and ran the roof gutter to it. If I were feeling more ambitious, I would move the first and second elbows to the top of the pipe so that I wouldn't have such a squirrelly combination of joints at the bottom ... but I'm not. Maybe next year. Hopefully it will look less odd when it is painted. ![]()
Then the second barrel was hooked up to the overflow from the first one, and the overflow from it was run into the remaining drainpipe with a short piece of hose. Voila! 110 gallons of rainwater to use in the garden. Eventually, when my side yard garden is back in shape, the overflow will be switched to a soaker hose. ![]()
While I was working in the side yard, I decided to close the opening in my fence to the neighbor's driveway that had gone in early in the project. ![]()
The first step was to roll it back into place. I repaired it by weaving in a few spirals from a discarded section of chain link, actually a pretty easy process.
![]()
Then it was just a matter of weaving the slats back into the chain link. ![]()
After that I moved around to the back of the garage, which will also have vinyl siding for the time being. ![]()
This area was even easier than the side transition because I wasn't working around any existing siding. ![]()
At the end of the week, once the floor in the office was done, I started cutting baseboards and door casings and getting them ready to paint. top |