My Remodel

Before
In the Beginning ...

Deconstruction
Teardown

Construction
Week 6 - The Footings
Week 7 - The Foundation
Week 8 - Plumbing
Week 9 - Backfill
Week 10 - Framing 1
Week 11 - Framing 2
Week 12 - Electrical
Week 13 - Siding 1 & Insulation
Week 14 - Siding 2
Week 15 - Drywall
My Vacation
Week 16 - Floors
Week 17 - Concrete & Electrical
Week 18 - Plumbing
Week 19 - Trim
Week 20 - Porch Rail
Week 21 - Concrete Finish
Week 22 - Punch List
Week 23 - Casings
Week 24 - Miscellaneous
Week 25 - Priming
Week 26 - Painting
Week 27 - Outside
Week 28 - Move In
Week 29 - Finishes
Week 30 - Garden
Week 31 - Permits
Week 32 - Flashing & Doors
Week 33 - Yard Work
Week 34 - Doors
Week 35 - Basement
Week 36 - Final Payment

On My Own
The List

Odd Bits
Unusual Aspects

HOME

Week 27 - Outside

This week started out with rain, but was supposed to clear later, so I decided to hold off painting for a while. Instead I worked on a variety of little jobs: finishing the floor in the office; getting stuff into the dumpster, since I'm having it picked up next week; retrofitting my garage sale find into another rain barrel - and modifying my existing rain barrel so they could be ganged together. I also picked up and dropped off a variety of materials, including a couple of mirrors from the The Rebuilding Center. One will go in the hall and the other is for the bathroom. Later in the week I moved back outside.

corner

The biggest task was the cement/vinyl siding transition, which I couldn't do until I got the necessary j-channel, but I had saved a lot of the old vinyl siding and I wanted to get everything I didn't need into the dumpster. For better access, the first thing was to drain and remove the existing rain barrel.

corner

As it turned out, the siding itself was relatively easy to replace, except where I had to work it under an already installed piece, but even that wasn't too difficult. I also wanted to remove the second unused ground drain and re-capping it because it obstructed the rain barrel. In the end I decided to pull up the pavers and cap it low enough that I could replace the pavers right over the top of it, which I did.

rain barrel

I put the first rain barrel back all the way into the corner, and ran the roof gutter to it. If I were feeling more ambitious, I would move the first and second elbows to the top of the pipe so that I wouldn't have such a squirrelly combination of joints at the bottom ... but I'm not. Maybe next year. Hopefully it will look less odd when it is painted.

rain barrel

Then the second barrel was hooked up to the overflow from the first one, and the overflow from it was run into the remaining drainpipe with a short piece of hose. Voila! 110 gallons of rainwater to use in the garden. Eventually, when my side yard garden is back in shape, the overflow will be switched to a soaker hose.

fence

While I was working in the side yard, I decided to close the opening in my fence to the neighbor's driveway that had gone in early in the project.

fence

The first step was to roll it back into place. I repaired it by weaving in a few spirals from a discarded section of chain link, actually a pretty easy process.

fence

Then it was just a matter of weaving the slats back into the chain link.

garage back

After that I moved around to the back of the garage, which will also have vinyl siding for the time being.

garage back

This area was even easier than the side transition because I wasn't working around any existing siding.

baseboard

At the end of the week, once the floor in the office was done, I started cutting baseboards and door casings and getting them ready to paint.


Week 28 - Move In

top