My Remodel

Before
In the Beginning ...

Deconstruction
Teardown

Construction
Week 6 - The Footings
Week 7 - The Foundation
Week 8 - Plumbing
Week 9 - Backfill
Week 10 - Framing 1
Week 11 - Framing 2
Week 12 - Electrical
Week 13 - Siding 1 & Insulation
Week 14 - Siding 2
Week 15 - Drywall
My Vacation
Week 16 - Floors
Week 17 - Concrete & Electrical
Week 18 - Plumbing
Week 19 - Trim
Week 20 - Porch Rail
Week 21 - Concrete Finish
Week 22 - Punch List
Week 23 - Casings
Week 24 - Miscellaneous
Week 25 - Priming
Week 26 - Painting
Week 27 - Outside
Week 28 - Move In
Week 29 - Finishes
Week 30 - Garden
Week 31 - Permits
Week 32 - Flashing & Doors
Week 33 - Yard Work
Week 34 - Doors
Week 35 - Basement
Week 36 - Final Payment

On My Own
The List

Odd Bits
Unusual Aspects

HOME

Week 7 - The Foundation

forms

Forms continued to go up on Saturday and early in the week in hopes of pouring on Monday. Sadly, on Monday morning the form work wasn't completed. Even more sadly, they didn't pass the first inspection, so more mysterious form work was done on Tuesday and they were reinspected. The walls were poured on Wednesday while I was away.

walls

On Thursday the forms started to come down and the foundation walls were revealed.

the garage

The garage was now defined well enough to begin recognizing what will be garage and what will be driveway. Notice the nifty jury-rigged drain that is temporarily carrying water away from the work area and into the parking lot next door. It is a couple of pieces of salvaged drain pipe, but it will come down as soon as the footings are secure.

I hope that I will be using it later to replace a drain on the east side of the house that was destroyed in the digging of the foundation. The drain was one I put in on the east side of my house to catch the runoff from my neighbor's roof and driveway, which was causing problems in my basement. That basement seepage has reappeared for the first time in six years and this is a dry year.

the basement wall

The missing basement/garage wall has begun to reappear, defining a somewhat dry storage area for project materials and tools.

retaining wall

Unfortunately there were also problems. Most obviously, what was supposed to be a side retaining wall for my remaining my front yard is instead an odd slice that slopes dramatically from the top of the foundation to the sidewalk. It is both too high at the foundation end and way too low at the sidewalk end. I am assured that it will be fixed.

finding level

More seriously, planned rafter pockets were found to be missing and the top of the wall was not entirely level. However, on Friday morning, the project foreman and the framer came out and marked all the errors, then the concrete guy went around the foundation with a roto-hammer correcting things.

framing 1

When that was done, the carpenter, Mike, laid a plastic vapor barrier inside the foundation, put a foam strip at the top of the foundation that apparently prevents air leaks.

framing 2

Then framing of the floor itself started which was very exciting for me.

framing 3

By the end of the day the floor joists were in and plywood was laid across them to recreate a walkway in the front.

stairs

The temporary stairs that Larry had built were stored in the back yard. We moved them back around to the front of the house and they were attached to the new framing, and voila! once again I have access to my own front door. At this point the floor joists are ready for inspection, but framing is over until the water line, gas line, plumbing for the new half bath, and drain lines are in place.


Week 8 - Plumbing

top