My Remodel

Before
In the Beginning ...

Deconstruction
Teardown

Construction
Week 6 - The Footings
Week 7 - The Foundation
Week 8 - Plumbing
Week 9 - Backfill
Week 10 - Framing 1
Week 11 - Framing 2
Week 12 - Electrical
Week 13 - Siding 1 & Insulation
Week 14 - Siding 2
Week 15 - Drywall
My Vacation
Week 16 - Floors
Week 17 - Concrete & Electrical
Week 18 - Plumbing
Week 19 - Trim
Week 20 - Porch Rail
Week 21 - Concrete Finish
Week 22 - Punch List
Week 23 - Casings
Week 24 - Miscellaneous
Week 25 - Priming
Week 26 - Painting
Week 27 - Outside
Week 28 - Move In
Week 29 - Finishes
Week 30 - Garden
Week 31 - Permits
Week 32 - Flashing & Doors
Week 33 - Yardwork
Week 34 - Doors
Week 35 - Basement
Week 36 - Final Payment

On My Own
The List

Odd Bits
Unusual Aspects

HOME

Week 6 - The Footings

forms for the foundation

By my calculations, we are now three weeks behind. At this pace the project will take more than six months, which isn't going to make me very happy. OTOH, they are finally putting things in instead of taking things out, so that's fun. You can see the big impressive hole where my basement wall used to be, the temporary support wall, and the big pile of dirt in my back yard.

The footing forms were set...

concrete guy

...and early in the week the concrete guy arrived and started preparations.

pouring concrete

Soon an alarming amount of concrete was being poured into various places in my yard.

working the concrete

Then it was quickly shaped and smoothed.

the driveway

The next day the forms were removed and (ta-da) actual concrete clearly defined the placement of my addition, garage and the retaining walls beside the driveway.

forms for the walls

After that forms started going up for the foundation walls that would sit on top of the new footings. Soon I had a forest of wood walls in front of the house ...

the garage

...a clearly defined garage area ...

from the front

... and where the retaining walls will be beside the driveway.

One addition at this point was to hook up my neighbor with the sub-contractor about the retaining wall on his side of the driveway.

The original plan called for a wall that gradually dropped, matching the slope behind it, until it tailed out at the sidewalk. With very little extra effort or cost, my neighbor arranged to have the wall come to the corner full height and merge into his concrete steps. Then the slope behind it would be leveled to the wall, which dramatically improves his yard.


Week 7 - The Foundation

top