
|
Before In the Beginning ... Deconstruction Teardown Construction Week 6 - The Footings Week 7 - The Foundation Week 8 - Plumbing Week 9 - Backfill Week 10 - Framing 1 Week 11 - Framing 2 Week 12 - Electrical Week 13 - Siding 1 & Insulation Week 14 - Siding 2 Week 15 - Drywall My Vacation Week 16 - Floors Week 17 - Concrete & Electrical Week 18 - Plumbing Week 19 - Trim Week 20 - Porch Rail Week 21 - Concrete Finish Week 22 - Punch List Week 23 - Casings Week 24 - Miscellaneous Week 25 - Priming Week 26 - Painting Week 27 - Outside Week 28 - Move In Week 29 - Finishes Week 30 - Garden Week 31 - Permits Week 32 - Flashing & Doors Week 33 - Yardwork Week 34 - Doors Week 35 - Basement Week 36 - Final Payment On My Own The List Odd Bits Unusual Aspects HOME |
Week 6 - The Footings![]() By my calculations, we are now three weeks behind. At this pace the project will take more than six months, which isn't going to make me very happy. OTOH, they are finally putting things in instead of taking things out, so that's fun. You can see the big impressive hole where my basement wall used to be, the temporary support wall, and the big pile of dirt in my back yard.
The footing forms were set... ![]()
...and early in the week the concrete guy arrived and started preparations. ![]()
Soon an alarming amount of concrete was being poured into various places in my yard. ![]()
Then it was quickly shaped and smoothed. ![]()
The next day the forms were removed and (ta-da) actual concrete clearly defined the placement of my addition, garage and the retaining walls beside the driveway. ![]()
After that forms started going up for the foundation walls that would sit on top of the new footings. Soon I had a forest of wood walls in front of the house ... ![]()
...a clearly defined garage area ... ![]() ... and where the retaining walls will be beside the driveway. One addition at this point was to hook up my neighbor with the sub-contractor about the retaining wall on his side of the driveway.
The original plan called for a wall that gradually dropped, matching the slope behind it, until it tailed out at the sidewalk. With very little extra effort or cost, my neighbor arranged to have the wall come to the corner full height and merge into his concrete steps. Then the slope behind it would be leveled to the wall, which dramatically improves his yard. top |